Estimating and Budgeting a Medium Scale Building Project A Case Study of a Proposed Departmet of Quantity Surveying at Kwara State.

ABSTRACT

This project, focus on preliminary activities that lead to draft bill of qualities for a propose multi-purpose studio hall, Ilorin. It’s centralized on preparation of bill of qualities for a studio hall and taking offs project.

Meanwhile, this is to prepare the construction legation and to understand the construction arrangement between the client and the client and the construction company,

TABLE OF CONTENTS

Title page                                                      i

Certification                                                  ii

Dedication                                                    iii

Acknowledgement                                         iv-v

Gratitude                                                      vi

Table of content                                            vii-x

CHAPTER ONE

1.0    Background Information                      1-3

1.1    Description of work                              3-4

1.2    Aims & Objectives                                4-5

1.3    Scope of the Project                              9-10

CHAPTER TWO

2.0    Title                                                     14

2.1    Location                                               14-16

2.2    Site Description                                    16-17

2.3    Accessibility                                         17-19

2.4    Availability and Proximity of Resource  19-20

2.5.   Definition of terms                                        26

CHAPTER THREE

3.0    General rules for taking-off                           37

3.1    Receipt of the drawings                                 37

3.2    Preliminary study of drawing                        37

3.3    Queries with the designers                            38-39

3.4    Organizing the work                                       39

3.5    Section of taking-off

3.6    Composition & Preparation of BOQ

3.7    Stages in BOQ

3.8    Method of bill preparation

3.9    Rules of Billing

CHAPTER FOUR

4.0    Sub Structures                                             40

4.1    Super Structure                                            40

4.2    Abstracting                                                   40-46

4.3    BOQ                                                             46-49

4.4    Quarry sheet and drawing plan                     49-50

CHAPTER FIVE

5.0    Summary                                                      57

5.1    Conclusion                                                   58-59

5.2    Recommendations

5.3    References                                           


 

Overall Rating

0

5 Star
(0)
4 Star
(0)
3 Star
(0)
2 Star
(0)
1 Star
(0)
APA

ABDULGAFAR, A , .A., M , HADI, A , .A., T , GANIYU, Y , RIDWAN, G , .A., A , .G., I , OLADAPO, A , .O., O , .O., A , OLUWABUSAYO, A , .O., I , IGE, F , KAFILAT, A , FAUSLAT, A , .O., U & .B., M (2021). Estimating and Budgeting a Medium Scale Building Project A Case Study of a Proposed Departmet of Quantity Surveying at Kwara State.. Afribary. Retrieved from https://afribary.com/works/estimating-and-budgeting-a-medium-scale-building-project-a-case-study-of-a-proposed-departmet-of-quantity-surveying-at-kwara-state

MLA 8th

ABDULGAFAR, ABDUL et. al. "Estimating and Budgeting a Medium Scale Building Project A Case Study of a Proposed Departmet of Quantity Surveying at Kwara State." Afribary. Afribary, 17 Dec. 2021, https://afribary.com/works/estimating-and-budgeting-a-medium-scale-building-project-a-case-study-of-a-proposed-departmet-of-quantity-surveying-at-kwara-state. Accessed 22 Nov. 2024.

MLA7

ABDULGAFAR, ABDUL, MUHAMMED .A. , ABDUL HADI , TAIWO .A. , YEKINI GANIYU , GHAFFAR RIDWAN , ADEBAYO .A. , IYIOLA .G. , ABRAHAM OLADAPO , OGUNDELE .O. , ABATI .O. , ADEWUMI OLUWABUSAYO , IBRAHIM .O. , FAGBEMI IGE , ALLI KAFILAT , AKINWALE FAUSLAT , UTHMAN .O. and MUHAMMED .B. . "Estimating and Budgeting a Medium Scale Building Project A Case Study of a Proposed Departmet of Quantity Surveying at Kwara State.". Afribary, Afribary, 17 Dec. 2021. Web. 22 Nov. 2024. < https://afribary.com/works/estimating-and-budgeting-a-medium-scale-building-project-a-case-study-of-a-proposed-departmet-of-quantity-surveying-at-kwara-state >.

Chicago

ABDULGAFAR, ABDUL , .A., MUHAMMED , HADI, ABDUL , .A., TAIWO , GANIYU, YEKINI , RIDWAN, GHAFFAR , .A., ADEBAYO , .G., IYIOLA , OLADAPO, ABRAHAM , .O., OGUNDELE , .O., ABATI , OLUWABUSAYO, ADEWUMI , .O., IBRAHIM , IGE, FAGBEMI , KAFILAT, ALLI , FAUSLAT, AKINWALE , .O., UTHMAN and .B., MUHAMMED . "Estimating and Budgeting a Medium Scale Building Project A Case Study of a Proposed Departmet of Quantity Surveying at Kwara State." Afribary (2021). Accessed November 22, 2024. https://afribary.com/works/estimating-and-budgeting-a-medium-scale-building-project-a-case-study-of-a-proposed-departmet-of-quantity-surveying-at-kwara-state